Kathleen Creedon | March 31, 2017
Controlled insurance program (CIP) feasibility analysis is the process of considering whether a CIP is a viable risk financing option for a project. The analysis should not only determine if a CIP is feasible but also whether it is the best risk financing approach among all possible options. A thorough feasibility analysis can help avoid unexpected or undesired outcomes resulting from a CIP.
In this two-part article, we describe a systematic process for evaluating the feasibility of implementing a controlled insurance program (CIP) that includes consideration of 10 key areas. In "Contemplating a Controlled Insurance Program," part one, we discussed the following five questions.
This part two will cover the five remaining questions that are useful to evaluate CIP feasibility.
A potential sponsor should consider current insurance market conditions, coverage availability, pricing, collateral requirements if applicable, and the required timeline for securing a program. Combined line programs—including workers compensation, general liability, and excess liability—are typically procured from standard markets. General liability only ("GL only") programs, especially for for-sale residential projects, are usually written by surplus lines markets. Some standard markets write GL only programs; however, their deductibles are typically much higher than in the excess and surplus markets, for example, $250,000 or $500,000 versus $10,000 or $25,000.
The sponsor's broker should have a complete understanding of the current CIP marketplace. An experienced broker's knowledge about each insurer's terms, conditions, and requirements for writing coverage is important as these factors may aid in a more accurate determination of feasibility. Some CIP insurers have mandatory safety requirements, such as requirements for a full-time site safety representative, drug screening, or 6-foot tie-off, which can add cost to a program. These additional costs, if not identified, can make a borderline program (a program with no or minimal savings projected) no longer feasible for a sponsor with the primary goal of savings.
It generally takes longer to market a combined line program than a GL only program. A rolling combined line program will usually take more time to arrange than a project for a single site. Currently, depending on the project, there may be as many as eight potential standard market insurers. A combined line program can take 8 to 12 weeks to market and place, which includes putting together a comprehensive submission, arranging for insurer site visits, obtaining quotations, reviewing and negotiating primary coverage terms, and agreeing on final pricing. It also takes additional time to approach excess markets once the primary program terms and pricing are finalized.
A GL only program, though simpler, can take 2 to 6 weeks to put together, especially for a program with high limits. An experienced broker can always arrange a program on a fast-track basis if needed; however, that approach is not ideal, as a CIP is a long-term engagement that should be carefully constructed because it affects multiple insureds.
Even with a capable broker and administrator, a combined line CIP can be administratively burdensome for an inexperienced sponsor over an extended period of time. There are usually other viable risk financing options available to an owner-sponsor in addition to the traditional approach (where contractors provide their own insurance) and an owner-controlled insurance program (OCIP). The sponsor and the broker should consider the sponsor's primary goals and its ability or inclination to manage a CIP over a long term.
For example, if the owners are considering an OCIP, their internal team is minimal, and they are primarily concerned about liability coverage and limits, a GL only OCIP, GL only contractor-controlled insurance program (CCIP), or a combined line CCIP may be a better choice than a combined line OCIP. CCIP sponsors also should consider their goals for implementing a program. A general contractor (GC) sponsor may wish to initially implement a GL only program that meets its coverage needs before diving into a combined line program that may require additional training of personnel and changes to internal procedures.
The party performing the feasibility analysis should always understand the sponsor's goals for the program and not make an assumption that the primary or only goal is savings, though that may sometimes be the case. All potential risk financing options should be explored, and an exercise like the following can ensure that goals are understood, promote discussion, and help a sponsor select a program that best meets its needs. It is also useful to prioritize objectives. This example is for a potential owner-sponsor.
# | Risk Financing Objective | Traditional | Combined Line OCIP | GL Only OCIP | CCIP |
---|---|---|---|---|---|
1 | Provides adequate coverage and high limits through statute of repose | Perhaps, depends on the GC | Yes | Yes | Yes |
2 | Provides opportunity for savings over traditional method | No | Yes, depends on adequacy of savings projections and program losses | Perhaps, not likely to be significant if high limits are purchased | Perhaps, if GC is willing to share, but not likely to be significant |
3 | Requires minimal administration duties of owner team | Yes | Perhaps, if OCIP administrator is capable and dedicated and there are minimal losses | Yes | Yes |
As shown in the above example, even without detailed financial data, each of the options has the potential to meet some or all of the sponsor's goals. A CCIP is not always available to an owner-sponsor, but the party performing the feasibility study should ask whether the GC is able to offer a CCIP and, if so, obtain the details for review. This step will ensure that the feasibility analysis is comprehensive. Such analysis, as shown above, may point out that the owner-sponsor should fully examine and understand their own administrative requirements in an OCIP and the potential administrator's capabilities, the scope of services, and ability to perform those duties over the life of the program.
A CIP pro forma, which is a projection of the expected financial outcome of a CIP using data estimated for the project and assuming the underlying assumptions will hold true, is usually the primary focus of a typical feasibility analysis. This topic is too comprehensive to be addressed in full here, and a more detailed discussion about how to understand, analyze, or best develop pro forma models will be addressed in a subsequent article. For this discussion, we'll look at how most pro formas are presented and the major pro forma components.
Combined line CIPs are not always presented or sold on the program cost alone. Raw cost numbers are not typically emphasized in a pro forma. Rather, the difference between traditional cost and CIP estimates are highlighted. To illustrate, imagine a scenario where a broker quotes a combined line CIP, for a $350,000,000 commercial project, with a $250,000 deductible, completed operations coverage through the statute of repose, and total limits of $100,000,000, for a cost of $8,000,000*. There would be some sticker shock associated with that cost number alone as contractor insurance cost is typically imbedded in the total cost of the work, and contractors do not typically identify their insurance costs in lump-sum bids. Because of this, CIP cost is almost always shown in a pro forma compared to the estimated cost of traditional insurance as shown in the highly simplified example below.
Item | Estimated Cost |
---|---|
Contractor insurance cost (traditional insurance procurement) | $9,000,000 A |
Minus | |
CIP program cost | $8,000,000A |
CIP financial result (savings or CIP benefit) | $1,000,000 |
A These numbers are for illustration purposes only. Program and contractor insurance costs vary by jurisdiction, program, and project type.
|
In the above example, which compares the estimated cost of traditional insurance to the estimated cost of a CIP, the benefit of implementing a CIP is shown as a savings of $1,000,000. Potential or expected savings are typically emphasized in a pro forma. However, it is important for a potential sponsor to understand that contractor insurance cost and CIP program cost figures are always "estimates based on estimates." These main components of the simplified pro forma formula, shown above, are based on an estimate of unburdened payroll. The following are descriptions of these key components of a pro forma.
When preparing, reviewing, or evaluating a pro forma, it is important to remember that there are three highly variable components that can affect the overall result: contractor insurance cost rates, unburdened payroll, and loss costs. None of these items are easy to predict, even with reliable data from previous projects, since there are many differences among projects. The best approach is to look at multiple scenarios for each variable. Many pro formas adequately address the loss-cost variable, presenting estimated financial results at various loss levels. Pro formas that show outcomes at various contractor insurance cost rates or alternative payroll estimates are less common. Although Monte Carlo simulations (providing multiple estimates, instead of a single estimate, for each component) may be useful to show a wider range of outcomes to a potential sponsor, such methods are not common.
Question number 8 above looks at how likely it is that an option will meet the sponsor's overall risk financing goals. For this last step, after considering potential financial outcomes and selection of the most viable or recommended option(s), we examine the advantages and disadvantages of each. It is important to be fully transparent about the potential downside(s) of each risk financing option. It is also important to realize that advantages and disadvantages will be interpreted from the perspectives of sponsor orientation, sponsor goals, and the attributes of the option itself. It is more common to find examples of the advantages of implementing a CIP in a feasibility study. The following are examples of some potential disadvantages of an OCIP that may be disclosed in a feasibility analysis and whose significance will be interpreted by the analyst and the sponsor.
Financial:
Administrative Burden Due to:
Risk Management/Other:
There are many methods for conducting a thorough feasibility analysis. In this two-part article, we have discussed one process for feasibility analysis that takes place on a continuum that starts with consideration of the CIP concept and extends through to closure of the CIP. Unfortunately, we do not always have the opportunity to work on the entirety of a project from beginning to end, from concept to ultimate completion, for up to 10 or more years (after the completed operations extension has exhausted), after all claims have been closed, and collateral, if applicable, is returned.
It would be highly informative to know the goals and aspirations of a sponsor at the beginning of a CIP, on what basis they were developed, and then be able to compare them to the result developed from real data at the end. If all parties with that kind of full knowledge and credible financial data got together to share and compare results in order to improve the feasibility analysis process, that would be CIP nirvana.
Opinions expressed in Expert Commentary articles are those of the author and are not necessarily held by the author's employer or IRMI. Expert Commentary articles and other IRMI Online content do not purport to provide legal, accounting, or other professional advice or opinion. If such advice is needed, consult with your attorney, accountant, or other qualified adviser.